Repository navigation
Expand file tree
/
Copy pathdelivery.py
More file actions
118 lines (80 loc) · 5.45 KB
/
Copy pathdelivery.py
File metadata and controls
118 lines (80 loc) · 5.45 KB
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61
62
63
64
65
66
67
68
69
70
71
72
73
74
75
76
77
78
79
80
81
82
83
84
85
86
87
88
89
90
91
92
93
94
95
96
97
98
99
100
101
102
103
104
105
106
107
108
109
110
111
112
113
114
115
116
117
118
# -*- coding: utf-8 -*-
"""
Created on Thu Mar 14 16:35:00 2019
@author: Alfonso
"""
line = list() #contains a single line
singleElement = list()
tasks = dict() #contains all the tasks
number = -1
fhand = open('cpm1.txt') #TWO FILES: cpm.txt and cpm1.txt
for line in fhand: #slide the file line by line
singleElement=(line.split(',')) #split a line in subparts
number += 1
for i in range(len(singleElement)): #creating the single task element
tasks['task'+ str(singleElement[0])]= dict()
tasks['task'+ str(singleElement[0])]['id'] = singleElement[0]
tasks['task'+ str(singleElement[0])]['name'] = singleElement[1]
tasks['task'+ str(singleElement[0])]['duration'] = singleElement[2]
if(singleElement[3] != "\n"):
tasks['task'+ str(singleElement[0])]['dependencies'] = singleElement[3].strip().split(';')
else:
tasks['task'+ str(singleElement[0])]['dependencies'] = ['-1']
tasks['task'+ str(singleElement[0])]['ES'] = 0
tasks['task'+ str(singleElement[0])]['EF'] = 0
tasks['task'+ str(singleElement[0])]['LS'] = 0
tasks['task'+ str(singleElement[0])]['LF'] = 0
tasks['task'+ str(singleElement[0])]['float'] = 0
tasks['task'+ str(singleElement[0])]['isCritical'] = False
# =============================================================================
# FORWARD PASS
# =============================================================================
for taskFW in tasks: #slides all the tasks
if('-1' in tasks[taskFW]['dependencies']): #checks if it's the first task
tasks[taskFW]['ES'] = 1
tasks[taskFW]['EF'] = (tasks[taskFW]['duration'])
else: #not the first task
for k in tasks.keys():
for dipendenza in tasks[k]['dependencies']: #slides all the dependency in a single task
#print('task ' + taskFW + ' k '+ k + ' dipendenza ' +dipendenza)
if(dipendenza != '-1' and len(tasks[k]['dependencies']) == 1): #if the task k has only one dependency
tasks[k]['ES'] = int(tasks['task'+ dipendenza]['EF']) +1
tasks[k]['EF'] = int(tasks[k]['ES']) + int(tasks[k]['duration']) -1
elif(dipendenza !='-1'): #if the task k has more dependency
if(int(tasks['task'+dipendenza]['EF']) > int(tasks[k]['ES'])):
tasks[k]['ES'] = int(tasks['task'+ dipendenza]['EF']) +1
tasks[k]['EF'] = int(tasks[k]['ES']) + int(tasks[k]['duration']) -1
aList = list() #list of task keys
for element in tasks.keys():
aList.append(element)
bList = list() #reversed list of task keys
while len(aList) > 0:
bList.append(aList.pop())
# =============================================================================
# BACKWARD PASS
# =============================================================================
for taskBW in bList:
if(bList.index(taskBW) == 0): #check if it's the last task (so no more task)
tasks[taskBW]['LF']=tasks[taskBW]['EF']
tasks[taskBW]['LS']=tasks[taskBW]['ES']
for dipendenza in tasks[taskBW]['dependencies']: #slides all the dependency in a single task
if(dipendenza != '-1'): #check if it's NOT the last task
if(tasks['task'+ dipendenza]['LF'] == 0): #check if the the dependency is already analyzed
#print('ID dipendenza: '+str(tasks['task'+dipendenza]['id']) + ' taskBW: '+str(tasks[taskBW]['id']))
tasks['task'+ dipendenza]['LF'] = int(tasks[taskBW]['LS']) -1
tasks['task'+ dipendenza]['LS'] = int(tasks['task'+ dipendenza]['LF']) - int(tasks['task'+ dipendenza]['duration']) +1
tasks['task'+ dipendenza]['float'] = int(tasks['task'+ dipendenza]['LF']) - int(tasks['task'+ dipendenza]['EF'])
#print('IF1 dip LS: '+str(tasks['task'+dipendenza]['LS']) +' dip LF: '+str(tasks['task'+dipendenza]['LF']) + ' taskBW: '+str(tasks[taskBW]['id'])+' taskBW ES '+ str(tasks[taskBW]['ES']))
if(int(tasks['task'+ dipendenza]['LF']) >int(tasks[taskBW]['LS']) ): #put the minimun value of LF for the dependencies of a task
tasks['task'+ dipendenza]['LF'] = int(tasks[taskBW]['LS']) -1
tasks['task'+ dipendenza]['LS'] = int(tasks['task'+ dipendenza]['LF']) - int(tasks['task'+ dipendenza]['duration']) +1
tasks['task'+ dipendenza]['float'] = int(tasks['task'+ dipendenza]['LF']) - int(tasks['task'+ dipendenza]['EF'])
#print('IF2 dip LS: '+str(tasks['task'+dipendenza]['LS']) +' dip LF: '+str(tasks['task'+dipendenza]['LF']) + ' taskBW: '+str(tasks[taskBW]['id']))
# =============================================================================
# PRINTING
# =============================================================================
print('task id, task name, duration, ES, EF, LS, LF, float, isCritical')
for task in tasks:
if(tasks[task]['float'] == 0):
tasks[task]['isCritical'] = True
print(str(tasks[task]['id']) +', '+str(tasks[task]['name']) +', '+str(tasks[task]['duration']) +', '+str(tasks[task]['ES']) +', '+str(tasks[task]['EF']) +', '+str(tasks[task]['LS']) +', '+str(tasks[task]['LF']) +', '+str(tasks[task]['float']) +', '+str(tasks[task]['isCritical']))