Note: All information relating to NV27 has been updated in the Network Updates Repo This discussion will cover the following for nv27: What about nv26?Public planning is happening for nv27 instead of nv26 since nv26 is use to implement the 90 day grace period discussed in FIP-0100:
|
Replies: 7 comments 43 replies
ScopeContext: Tentative Timeline:
Legend:
|
Timelines (Tentative and requesting for review)
|
Network Upgrade Name - Golden Week Upgrade |
Other |
|
From my side, FIP 0101 and FIP 0082 are the two FIPs that are "Accepted" but not "Final". If there are no objections, I would prioritize adding them to the NV'27 upgrade. I'll add more FIPs in the pipeline as I clean up statuses and drafts this week, but just wanted to scope this pipeline in the open. Links: |
|
Context: Tentative Timeline:
Legend:
|
|
建议将主网升级时间设置在 11 月 1 日之后 |
Scope
Context:
This table summarizes the revised Network Upgrade (NV27) FIPs queue discussed during Core Devs Meeting 82.
It reflects the latest status, timeline considerations, and prioritization of proposals based on Core Devs 82 discussions.
Tentative Timeline:
The NV27 upgrade planning starts with a target code freeze date of August 31, 2025.
ExtendSectorExpirationmethod