Milestones
List view
Remaining P2 functionality and hardening, in epic order. Holds more than one milestone of work; what does not fit is re-planned at the next round.
Due by December 15, 2026New functionality, P1 first: change review and the run journal (brig-sh/brig#301), egress enforcement (brig-sh/brig#302), persistent sessions.
Due by November 30, 2026Usability P2s: one consistent CLI, agent profiles and skills, and the docs.
Due by November 15, 2026Usability P1s (hull lifecycle, image pulls, the exec deadline, the Linux bundle) and the secrets broker slice of brig-sh/brig#302.
Due by October 31, 2026•0/3 issues closedEvery P0 lands here: brig-sh/brig#237, #30, #235, #264, #413 and brig-sh/hull#17, #94, with the work already in review and the first usability P1s. Planned against measured capacity.
Overdue by 1 day(s)•Due by October 13, 2026